top of page

GRS Projects - Massachusetts

This page summarizes active and completed GRS Development and Testing project activity in Massachusetts and provides a link to access all completed GRS documents. For all completed projects, Meeting Summaries and each project Site Selection Matrix are available. Contact EPA Region 1 or Nuka Research via the contact information provided on the Home Page to obtain project documents.

Active Projects

GRS Development

Housatonic River

August 2023 - August 2024

A total of 10 GRS will be developed for the Housatonic River in Massachusetts

 

An Initial Work Group/Site Selection Meeting and Final Work Group Meeting will be held over the course of this project and all work group members will be invited to attend. Field site surveys will also be conducted and a Tactics Sub-Group meeting will be conducted following the site surveys to develop GRS tactics prior to final GRS production. Meeting and event information is included below. Additional project information will be shared with the work group throughout the life of this project. For project related inquieries, contact EPA Region 1 or Nuka Research via the contact information provided on the Home Page.

Meeting/Event

Initial Work Group/Site Selection

Date/Time
Location
Documents

Thursday, November 16, 2023

1pm - 3pm

Zoom video conference

Site Surveys

Wednesday, April 24, 2024 9am-2pm

See Site Survey Schedule

Tactics Sub-Group

Final Work Group

TBD

TBD

TBD

TBD

Pending

Pending

GRS Validation/Testing
Blackstone River (MA & RI)
August 2023 - August 2024

1 exisiting GRS will be selected for testing and validation in Massachusetts

1 exisiting GRS will be selected for testing and validation in Rhode Island

Meeting/Event
Date/Time
Location
Documents

Initial Planning

Tuesday, October 31

10:30am - 12:00pm

Zoom video conference

Agenda

Final Planning

Tuesday, April 2

10:00am - 11:00am

Field Validation/Testing

Wednesday, June 5

Zoom video conference

Pending

Pending

Blackstone River Valley Heritage Center, Worcester

Site of BR-MA-01A

Completed Projects

2021 - 2022 Connecticut River GRS Development Project

This project was completed in 2022.  The 10 Geographic Response Strategies that were developed are listed below and are available at the Regional Response Team 1 website located here.

CR-MA-01A Northfield/Pauchaug Boat Ramp

CR-MA-01B Northfield/Riverview Picnic Area

CR-MA-01C Northfield/Millers River

CR-MA-02   Turners Falls

CR-MA-03   Sunderland

CR-MA-04A Hadley-Hatfied/Hatfield Boat Launch 

CR-MA-04B Hadley-Hatfied/Mill River

CR-MA-05 Northhampton-Hadley/Elwell Island

CR-MA-06 Easthampton/Oxbow Boat Ramp

CR-MA-07A Holyoke/S. Hadley/Dry Brook

CR-MA-07B Holyoke/S. Hadley/Brunelle's Marina

CR-MA-07C Holyoke/S. Hadley/Cove Island/Holyoke Dam

CR-MA-08 Chicopee/Chicopee River

CR-MA-09 Springfiled/W. Springfield

CR-MA-10 Agawam/Westfield River

2019 - 2020 Blackstone River GRS Development Project

This project was completed in 2020.  The 10 Geographic Response Plans that were developed are listed below and are available at the Regional Response Team 1 website located here.  

BR-MA-01 Worcester

BR-MA-02 Millbury North

BR-MA-03 Millbury South

BR-MA-04 Sutton/Tricentennial Park

BR-MA-05 Grafton

BR-MA-06 Riverdale Dam

BR-MA-07 Plummer's Landing

BR-MA-08 Rice City Pond

BR-MA-09 Uxbridge/Stanley Woolen Mill

BR-MA-10 Uxbridge/River Rd.

2013 - 2014 Merrimack & Charles River GRS Development Project

This project was completed in 2014.  The 10 Geographic Response Plans that were developed are listed below and are available at the Regional Response Team 1 website located here.  

Merrimack River

MR-MA-01 Haverhill

MR-MA-02 Lawrence

MR-MA-03 Pine Island

MR-MA-04 Lowell

MR-MA-05 North Chelmsford/Tyngsborough

Charles River

CH-MA-01 Gridley Locks/Museum of Science

CH-MA-02 Magazine Beach

CH-MA-03 Bleachery Dam

CH-MA-04 Moody St. Dam

CH-MA-05 Norumbega

bottom of page